Saturday, 5 March 2011

PAL Experience in Oil & Gas

ONSHORE GAS PROCESSING FACILITIES – OYONG PHASE2









Owner : SANTOS (SAMPANG) PTY. LTD
Client : SANTOS (SAMPANG) PTY. LTD
Bidder role : Main Contractor
Construction Location : PT PAL Indonesia’s Shop.
PT. Indonesia Power – Grati, Pasuruan Site Construction Location
Project Duration : 19 (Nineteenth) Months, February 2008 – September 2009.
Plant Location : PT. Indonesia Power – Grati, Pasuruan
Project Scope : Engineering, Procurement, Installation and Commissioning (EPIC)
Contract Value : above 19 Million USD.
Total Approx. Weight : N/A
Brief Description :
Onshore Gas Processing Facility


With major equipments :
1. Pressure Vessels & Tanks.
2. ESD System.
3. Process Control System
4. Chemical Injection.
5. Gas-gas Exchanger.
6. Dew Point Refrigeration Package.
7. Pig Receiver.
8. TEG Contactor.
9. Separators.
10. TEG Regeneration Package.
11. Dew Point Chiller Package.
12. Gas Engine Generator.
13. Gas Metering Package.
14. Diesel Generator.
15. Gas Turbine Generator.
16. Fire Detection System
17. Fire Water System,
18. Concrete Control Room
19. Telecommunication System.

Detail of Work :
1. Front End Engineering Design Evaluation, optimization and verification.
2. Fabrication Engineering.
3. Procurement Services for Civil Structure, Static and Rotating Mechanical Equipment, Steel Structure, Raw Material, Piping & Instrumentation, Control System, Electrical and Bulk Material
4. Pressure Vessel, Piping and Structure Fabrication.
5. Static Mechanical Equipment Fabrication and Installation.
6. Piping, Electrical & Instrumentation, Control & System Installation.
7. Civil works for Plant Construction.
8. Tie-in with PT Indonesia Power Gas Receiving Mater.
9. Tie-in with Offshore Pipeline for Oyong Phase 2 Contractors.
10. Start-Up and Commissioning.
-------------------ONSHORE FABRICATION SERVICE FOR KE-32 PLATFORM

Owner : KODECO ENERGY CO, LTD
Client : KODECO ENERGY CO, LTD
Bidder role : Main Contractor
Construction Location : PT PAL Indonesia’s Shop.
Project Duration : 12 (Twelve) Months, May 2006 –May 2007
Platform Location : Madura Strain
Project Scope : Engineering, Procurement and Construction (EPC)
Contract Value : above 4 Million USD.
Total Approx. Weight : 1000 Tonnes consist of Platform, Pile, Jacket & Equipment

Brief Description : Monopod Platform.
With major equipments :
1. Pressure Vessels.
2. ESD System.
3. MPFM.
4. WHCP.
5. Scada System.
6. Close Drain System.
7. Chemical Injection.
8. N2 Bottle system.
9. Pedestal Crane Package, etc





Detail of Work :
1. Engineering Evaluation and verification.
2. Fabrication Engineering.
3. Procurement Services for Steel Structure Raw Material, Piping & Instrumentation, Electrical and Bulk Material.
4. Platform Steel Structure Fabrication.
5. Pile & Jacket Steel Structure Fabrication.
6. Mechanical Equipment Fabrication and Installation.
7. Piping, Electrical & Instrumentation Installation.
8. Pre-Commissioning, Load Out and Sea Fastening.
-------------------
WELLHEAD PLATFORM – A UJUNG PANGKAH DEVELOPMENT PROJECT
Owner : AMERADA HESS
Client : AMERADA HESS
Bidder role : PAL- RPE Consortium
Construction Location : PT PAL Indonesia Shop.
Project Duration : May 2005 - September 2006
Platform Location : Ujung Pangkah - Gresik Madura Strain
Project Scope : Engineering, Procurement, Construction and Installation (EPIC)
Contract Value : above 60 Million USD.
Total Approx. Weight : 1300 Tonnes consist of Platform, Pile & Jacket











Project Scope :
1. Engineering Evaluation and Verification.
2. Procurement Services for Equipment, Steel, Super Duplex Material, Electrical, Instrumentation and Bulk Material.
3. Fabrication Engineering.
4. Fabrication Pile & Jacket and Platform Steel Structure.
5. Installation of Mechanical Equipment and Piping, Electrical & Instrumentation
6. Fabrication and Installation Subsea Pipeline 18” (42 km).
7. Pre-Commissioning and Commissioning.

Brief Description :
Four (4) Legs Platform, with major equipments :
1. Pressure Vessels.
2. ESD System.
3. PCS System.
4. F&G Detection System.
5. MPFM.
6. WHCP.
7. Scada System.
8. Close Drain System.
9. Chemical Injection.
10. N2 Bottle system.
11. Pedestal Crane Package.
12. Diesel Generator Package, etc
-------------------
ZELDA F PLATFORM FABRICATION FOR SES GAS PROJECT

Owner : CNOOC SES LTD
Client : CNOOC SES LTD
Bidder role : Main Contractor
Construction Location : PT PAL Indonesia Shop.
Project Duration : June 2005 - January 2006
Platform Location : South East Sumatera Gas Project (Zelda F) - Madura Strain
Project Scope : Engineering, Procurement and Construction (EPC)
Contract Value : above 4 Million USD.
Total Approx. Weight : 685 Tonnes consist of Platform, Pile, Jacket & Equipment
Brief Description :
Monopod Platform.
With major equipments :
1. Pressure Vessel.
2. Heat Exchanger.
3. ESD System.
4. MPFM.
5. WHCP.
6. Scada System.
7. Dew Point Control System.
8. Close Drain System.
9. Chemical Injection.
10. N2 Bottle system.
11. Pedestal Crane Package, etc

Detail of Work :
1. Fabrication Engineering.
2. Procurement Services for Steel Structure Raw Material, Piping & Instrumentation, Electrical and Bulk Material
3. Platform Steel Structure Fabrication.
4. Pile & Jacket Steel Structure Fabrication.
5. Mechanical Equipment Installation.
6. Piping & Instrumentation Installation.
7. Pre-commissioning, Load Out and Sea Fastening.
-------------------
TOTAL TUNU PHASE VII, VIII, XI / PKG1
Owner : TOTAL INDONESIE
Client : TOTAL INDONESIE
Equipment : Turbo Compressor Module Package.
Quantity : 2 (two) Units
Bidder role : Contractor
Activity Location : GE Nuovo Pignone Florence & Massacarrara - Italia
Project Duration :
Phase XI Oct 2006 – Febr. 2008.
Phase VIII Sept. 2001 - April 2003
Phase VII August 1998 - April 2000
Project Scope :
Management, Engineering, Procurement, Construction and CommissioningContract Value :
Phase XI above 38 Million USD.
Phase VIII above 28 Million USD
Phase VII above 31 Million USD
Total Approx. Weight : 800 Tonnes
Brief Description :
Compressor for Wellhead Gas Lift
With major equipments :
1. Gas Turbine.
2. Compressor.
3. Instrumentation.
4. Electric and Control System.
5. Steel Structure etc

Detail of Work :
1. Basic and Detail Engineering.
2. Fabrication Engineering.
3. Procurement Services for Steel Structure Instrumentation, Electrical and Bulk Material
4. Steel Structure Fabrication.
5. Mechanical Equipment Installation.
6. Piping & Instrumentation Installation.
7. Electrical Installation.
8. Load Out and Transportation.
9. Package Installation.
10. Commissioning.
11. Project Management.
Equipment Destination : East Kalimantan - Indonesia
-------------------
ARII CCO-341 PROJECT
Owner : ARCO INDONESIA
Client : ARCO INDONESIA
Equipment : Compressoion Modules Train C and D.
Quantity : 2 (two) Units
Bidder Role : Contractor
Activity Location : PT PAL Indonesia Shop
Project Completion : 1997
Project Scope : Engineering, Procurement, and Construction.
Contract Value : above 3 Million USD
Total Approx. Weight : 600 Tonnes
Brief Description :
Compressor for Wellhead Gas Lift with dimension of 20 (L) x 75 (W) x 12 (H)
With equipment :
1. Gas Turbine.
2. Compressor.
3. Instrumentation.
4. Electric and Control System.
5. Steel Structure.

Detail of Work :
1. Fabrication Engineering.
2. Procurement Services for Steel Structure Raw Material, Equipment, Piping & Instrumentation, Electrical and Bulk Material
3. Steel Structure Fabrication.
4. Mechanical Equipment Installation.
5. Piping & Instrumentation Installation.
6. Electrical Installation.
7. Load Out and Transportation.
Equipment Destination : Bontang - Indonesia
-------------------
ARII CCO-300 PROJECT
Owner : ARCO INDONESIA
Client : ARCO INDONESIA
Equipment : Monopod Platform and Pipespool.
Quantity : ea 1 (one) Unit.
Bidder Role : Contractor
Activity Location : PT PAL Indonesia Shop
Project Completion : 1995
Project Scope : Procurement and Construction.
Contract Value : above 1 Million USD
Total Approx. Weight : N/A
Brief Description : Fabrication of KLC Monopod Platform and Pipespool for MMC-A Enhancement

Detail of Work :
1. Fabrication Engineering
2. Procurement Services.
3. Machining
4. Construction.
5. Load Out and Transportation.
-------------------ARII CCO-283 PROJECT
Owner : ARCO INDONESIA
Client : ARCO INDONESIA
Equipment : Package.
Quantity : 1 (one) Set.
Bidder Role : Contractor.
Activity Location : PT PAL Indonesia Shop
Project Completion : 1995
Project Scope : Installation.
Contract Value : above 1 Million USD
Total Approx. Weight : N/A
Brief Description : KNA/BM Relocation

Detail of Work :
1. Mobilization
2. Transportation.
3. Installation.
-------------------
MODULAR PACKAGE OF RECOVERY PLUS FOR BLUESKY PROJECT
Owner : PERTAMINA – UP VI BALONGAN
Client : UOP
Equipment : Glycol Regeneration Package.
Quantity : 1 (one) Unit
Bidder role : Subcontractor
Construction Location : PT PAL Indonesia Shop
Equipment Delivery : August, 2004
Project Scope : Engineering, Procurement, Construction & Pre-Commissioning
Contract Value : above US$. 1,500,000
Total Approx. Weight : 100 Tonnes
Brief Description :
The package consist of :
1. Steel Structure.
2. Heat Exchanger
3. Pressure Vessels.
4. Tanks.
5. Piping.
6. Electrical.
7. Instrumentation.
8. Bulk Materials.

Detail of Work :
1. Detail Engineering.
2. Fabrication Engineering.
3. Procurement Services.
4. Fabrication, Machining
5. Installation.
6. Pre-Com, Load Out & Installation
Destination : Balongan
-------------------
GLYCOL REGENERATION PACKAGE PROJECT

Owner : MOBIL OIL
Client : MOBIL OIL
Equipment : Glycol Regeneration Package.
Quantity : 2 (two) Units.
Bidder role : Contractor
Construction Location : PT PAL Indonesia Shop.
Project Duration : October 1995 - July 1996
Project Scope : Engineering, Procurement, and Construction.
Contract Value : above 1,500,000 Million USD Approx.
Total Approx. Weight : 80 Tonnes
Brief Description :
The package consist of :
1. Steel Structure.
2. Interchanger.
3. Pressure Vessels.
4. Tanks.
5. Burner.
6. Piping.
7. Instrumentation.
8. Bulk Materials.

Detail of Work :
1. Detail Engineering.
2. Fabrication Engineering.
3. Procurement Services.
4. Fabrication, Machining and Construction.
5. Load Out and Transportation.
Destination : South Lhoksukon, Aceh
-------------------
NILAM, SEMBERAH S-13 AND PAMAGUAN GAS COMPRESSION
Owner : BRITISH PETROLEUM
Client : VICO INDONESIA
Equipment : Air Cooled Heat
Quantity : 1 (One) Unit
Bidder role : Contractor
Construction Location : PT PAL Indonesia
Project Duration : July 1998 - December
Project Scope : Engineering, and Construction.
Contract Value : above USD 500,000.
Total Approx. Weight : 95 Tonnes
Brief Description : N/A

Detail of Work :
1. Detail Engineering.
2. Fabrication Engineering
3. Procurement Services.
4. Fabrication, Machining and Construction.
5. Load Out.
Destination : Franco On Barge
-------------------
SINGLE BUOY MOORING KODECO
Owner : KODECO ENERGY CO. LTD
Client : KODECO ENERGY CO. LTD
Equipment : Oil Mooring Barge.
Quantity : One (1) Unit
Bidder role : CONTRACTOR
Activity Location : PT PAL Indonesia Shop
Equipment Delivery : August, 2001
Project Scope : Repair and Maintenance.
Contract Value : -
Total Approx. Weight : 150 Tonnes
Brief Description : N/A.
Detail of Work :
1. Fabrication Engineering
2. Procurement Services.
3. Repair